Key numbers
- Moist curing: 5 days at ≥70 °F (21 °C), 7 days at 50–70 °F (QUIKRETE)
- Freeze protection: first 48 hours (QUIKRETE, Sakrete)
- Strength: 2,500 psi (17.2 MPa) at 7 days, 4,000 psi (27.5 MPa) at 28 days for bagged concrete mix
- 7-day strength = 62.5% of the 28-day rating (calculated from the data sheet)
- Fence posts: wait 24 hours before any strain (QUIKRETE)
On this page
- How to use the Concrete Curing Time
- How long does concrete take to cure?
- How strong is concrete at 7 and 28 days?
- When can you walk on new concrete?
- When can you drive on a new concrete driveway?
- How do you cure concrete properly?
- Does temperature change concrete curing time?
- Is curing the same as drying?
- How long before setting posts, forms and loads?
- What can go wrong if concrete is not cured?
- Our take
- Frequently asked questions
How to use the Concrete Curing Time
- 1Pick your unitsEvery dimension has its own unit menu (in, ft, yd, cm or m); changing one converts that number so the size stays the same. The US / Metric switch sets all fields to feet and inches or meters and centimeters and resets them to typical values.
- 2Enter the dimensionsType the length (default feet), width (default feet) or thickness (default inches). Measure the inside of the forms and the depth in several places.
- 3Set waste and quantityUse the waste slider (0 to 20%, default 10%) and allow more on uneven ground. If you have several identical pours, enter how many.
- 4Read the resultsSee the volume in cubic yards, cubic feet and cubic meters, the ready-mix order rounded up to ¼ yard, the number of 90, 80, 60, 50 and 40 lb bags rounded up, and the weight at the density you choose (150, 145 or 140 lb/ft³).
- 5Price it and save itPick a pricing basis (per cubic yard, per cubic meter or per bag of the highlighted size) and enter your local price for a material cost. Use Add to project to total several pours, and Copy link to share the exact result.
Results update as you type. Back to the calculator ↑

The calculator above sizes the pour; this page covers what happens after the last float pass. Most curing questions come down to three dates: when the moist-curing period ends, when the concrete is safe from frost, and when it reaches the strength it was sold at. The figures below come from manufacturer data sheets. Where no primary source gives a number (walk-on and drive-on times are the main gap), the page says so instead of guessing.
How long does concrete take to cure?
Short answer: keep it wet 5–7 days, guard it from frost for 48 hours, and count on rated strength at 28 days.
“Curing” means keeping enough water and warmth in fresh concrete for the cement to keep hydrating. QUIKRETE’s Concrete Mix data sheet puts it plainly: curing “should be started as soon as possible and should continue for a period of 5 days in warm weather at 70 ºF (21 ºC) or higher or 7 days in colder weather at 50 ºF to 70 ºF (10 ºC to 21 ºC).” Sakrete’s High-Strength Concrete Mix sheet asks for 3 to 5 days of keeping the surface moist. Both sheets say to protect the work from freezing for the first 48 hours.
| Milestone | Timing | Source |
|---|---|---|
| Start curing | As soon as the surface can take it without damage | QUIKRETE |
| Freeze protection | First 48 hours | QUIKRETE, Sakrete |
| Strain on a fence post | After 24 hours | QUIKRETE |
| Moist curing, ≥70 °F (21 °C) | 5 days | QUIKRETE |
| Moist curing, 50–70 °F (10–21 °C) | 7 days | QUIKRETE |
| Moist curing (Sakrete High-Strength) | 3–5 days | Sakrete |
| 7-day strength | 2,500 psi (17.2 MPa) | QUIKRETE, ASTM C39 test |
| Rated strength | 4,000 psi (27.5 MPa) at 28 days | QUIKRETE, Sakrete |
Below 50 °F (10 °C) neither sheet gives a curing period. That is cold-weather concreting, where blankets, heated enclosures or accelerated mixes come in; ask the supplier before pouring rather than stretching the 7-day figure.
How strong is concrete at 7 and 28 days?
Short answer: bagged concrete mix is rated about 2,500 psi at 7 days and 4,000 psi at 28 days, so it has about five-eighths of its strength after one week. Which psi a garage floor or porch needs in the first place is covered in concrete psi.
Strength is measured by crushing cylinders under ASTM C39. QUIKRETE publishes two points for its general-purpose Concrete Mix:
| Age | Compressive strength (psi) | (MPa) | Share of 28-day rating |
|---|---|---|---|
| 7 days | 2,500 | 17.2 | 62.5% |
| 28 days | 4,000 | 27.5 | 100% |
The 62.5% is our arithmetic (2,500 ÷ 4,000), not a published curve. We do not show 1-, 3- or 14-day values because the data sheets do not give them, and the shape of the curve depends on cement type, water content, admixtures and temperature. Ready-mix concrete ordered by strength class follows its own mix design; the 28-day rating on the ticket is the one that counts.
Why 28 days? It is the standard reference age for specifying and testing concrete. Concrete does not stop there, but the rated number on the bag or the ticket means “at 28 days, cured as the sheet says.”
When can you walk on new concrete?
Short answer: no primary source we accept gives a fixed walk-on time for general concrete, so judge the surface, not the clock.
Neither the QUIKRETE nor the Sakrete general-purpose sheet names a walk-on hour. Rules of thumb you will see online (often “24 to 48 hours”) cannot be cited to a standard or data sheet, so we do not endorse them; cold weather pushes any such figure later. Ask your supplier or finisher about the mix you poured. Before you step on it:
- The surface should be hard enough that a fingernail does not mark it and a shoe leaves no print.
- Keep foot traffic off the edges and joints, which chip most easily.
- Lift the curing cover only as long as needed and put it back; walking on it is not a reason to stop curing.
- Keep dragging furniture, ladders and wheelbarrows off until the moist-curing period is over.
If you used a fast-setting product, its own bag and data sheet govern; those mixes are formulated to be loaded sooner and are outside the numbers on this page.
When can you drive on a new concrete driveway?
Short answer: wait at least until the moist-curing period is over, and longer for heavy vehicles or cool weather. No data sheet we checked gives a drive-on day.
What the data does say: at 7 days, bagged concrete has 62.5% of its rated strength. Early-age concrete is also more vulnerable at edges and joints, and a soft subgrade concentrates load. Heavier loads (a delivery truck, a loaded trailer, an RV) are a reason to wait at least until the 28-day rating age, and to get the opening date from your supplier, contractor or engineer.
For a ready-mix driveway, the supplier knows the mix and can tell you when it reaches the strength you need; some contractors break test cylinders before opening a slab to traffic. If your contract does not name a date, ask for one in writing.
How do you cure concrete properly?
Short answer: stop the water from leaving. Cover it, wet it, or seal it with a curing compound.
QUIKRETE lists these methods, all of which aim to keep the surface continuously moist:
| Method | How | Watch out for |
|---|---|---|
| Curing compound (cure and seal) | Spray, brush or roll once the surface is hard; damp, not wet | Not if rain or below 50 °F (10 °C) is expected within 24 h; not in late fall where deicers will be used |
| Plastic sheeting | Lay flat, seal the laps, weigh down the edges | Can discolor colored concrete in patches |
| Wet burlap | Place once hard enough; sprinkle to keep wet | Use washed, chemical-free burlap; can discolor colored concrete |
| Sprinkler or soaker hose | Keep the whole surface wet | Must be continuous; on-and-off wetting interrupts curing |
Hot, dry or windy days are the hardest. QUIKRETE warns that evaporation in those conditions “will hinder the hydration reaction” and can cause finishing problems and shrinkage cracking. Start curing as early as the surface allows.
Worked example: 10 × 12 ft patio, 4 in thick
- Volume: 10 × 12 × (4 ÷ 12) = 40 ft³ (1.48 yd³, 1.133 m³)
- Bagged mix: 40 ÷ 0.60 = 67 bags of 80 lb (or 89 bags of 60 lb)
- Plastic for curing, 1 ft overlap on every side: 12 × 14 = 168 ft² (15.6 m²)
- Poured on a 75 °F day: keep it covered or wet for 5 days; at 60 °F, 7 days
- Expected strength: about 2,500 psi at day 7, 4,000 psi at day 28 (QUIKRETE Concrete Mix)
Worked example: 3 × 3 m pad, 100 mm thick
- Volume: 3 × 3 × 0.1 = 0.9 m³ (31.78 ft³)
- Bagged mix: 31.78 ÷ 0.60 ft³ = 53 bags of 80 lb (36.2 kg)
- Plastic sheet with 300 mm overlap each side: 3.6 × 3.6 = 12.96 m²
- At 15 °C (between 10 and 21 °C): moist-cure for 7 days; frost-protect the first 48 hours
Does temperature change concrete curing time?
Short answer: yes. Cold slows hydration, heat speeds water loss, and freezing in the first 48 hours can damage the concrete.
| Air temperature | What changes | Guidance |
|---|---|---|
| 70 °F (21 °C) and up | Faster hydration, faster evaporation | Moist-cure 5 days; start early, shade and wet on hot, windy days |
| 50–70 °F (10–21 °C) | Slower strength gain | Moist-cure 7 days |
| Below 50 °F (10 °C) | Hydration slows considerably | Not covered by the general sheets; plan cold-weather protection with your supplier; no curing compound if below 50 °F within 24 h |
| Below 32 °F (0 °C) in the first 48 h | Risk of freeze damage | Plastic sheeting and insulating blankets (QUIKRETE) |
The 5- and 7-day periods assume the concrete itself stays in those ranges. Overnight lows count: a mild afternoon followed by a 35 °F night puts you in the colder row.
Is curing the same as drying?
Short answer: no, and confusing them leads to bad decisions.
Curing keeps water in so the cement keeps reacting. Drying is water leaving. A slab can be well cured and still far too wet for vinyl, wood or epoxy. If flooring or a coating is going over the concrete, the product maker’s moisture test and limit decide when, not the curing table above. Sealers are a separate case: a cure-and-seal product is applied during curing by design, while a penetrating or decorative sealer usually waits; follow its label.
How long before setting posts, forms and loads?
Short answer: posts after 24 hours (no strain), form stripping per your supplier or plans (no data sheet we checked gives a time), structural loads per your engineer or building code.
| Job | Earliest step | Source or basis |
|---|---|---|
| Fence post (10 in hole, 3 ft deep: 1.64 ft³, 3 × 80 lb bags) | Any strain after 24 h | QUIKRETE |
| Slab or patio, light foot traffic | Surface hard and unmarked; no fixed hour | No primary source; judge the surface |
| Driveway, cars | After moist curing at minimum; ask supplier | 62.5% of rating at 7 days |
| Heavy vehicles, equipment | Not before 28-day rated strength; confirm with supplier or engineer | Data sheet rating age |
| Load-bearing footing | Per local building code / engineer | QUIKRETE refers to codes |
What can go wrong if concrete is not cured?
Short answer: lower strength, a weaker and dustier surface, and more cracking.
QUIKRETE’s sheet says proper curing “increases the strength and durability of concrete, and a poor curing job can ruin an otherwise well-done project.” The surface dries first, so it is the part that suffers most: the top layer is what sees tires, salt, and freeze-thaw cycles. In practice that shows up as scaling, dusting and shrinkage cracks. The fix is simple: for the patio above, 168 ft² of plastic sheeting or a coat of curing compound.
Our take
The question people ask (“how long until I can use it?”) does not have a single honest number, and pages that print one usually do not cite it. The dependable numbers are the ones on the bag: 5 or 7 days of moist curing depending on temperature, 48 hours of frost protection, 24 hours before stressing a post, and the strength ratings at 7 and 28 days. Plan around those, and get the walk-on and drive-on dates from whoever mixed your concrete.
FAQ
Frequently asked questions
How long does concrete take to cure?
Keep it moist for the first 5 days in warm weather (70 °F / 21 °C or higher) or 7 days at 50–70 °F, per the QUIKRETE Concrete Mix data sheet. Strength keeps rising after that; the rated 4,000 psi is a 28-day value. Hydration continues slowly for months, so cured is a matter of degree, not a single day.
How long before you can walk on new concrete?
Neither the QUIKRETE nor the Sakrete general-purpose data sheet gives a walk-on time, so treat any single number with caution. Cold weather pushes any rule of thumb later. Wait until the surface is hard, unmarked by a fingernail, and keep the curing cover on.
When can you drive on a new concrete driveway?
No manufacturer sheet we checked gives a drive-on day for general concrete. What the data does show is that bagged mix reaches only 62.5% of its 28-day strength at 7 days (2,500 of 4,000 psi). Ask your ready-mix supplier or finisher for the mix they poured, and wait longer in cool weather or for heavy vehicles.
How long does concrete take to dry vs cure?
They are different things. Curing is keeping water in the concrete so the cement can hydrate and gain strength; you want it to stay damp. Drying is moisture leaving the slab, which matters before flooring or coatings go on and can take far longer than curing. Follow the flooring maker's moisture test, not a day count.
Should I water new concrete, and for how long?
Yes, or cover it. QUIKRETE lists a lawn sprinkler, soaker hose, wet burlap, plastic sheeting or a curing compound, applied as soon as the surface can take it and continued 5 days at 70 °F or warmer, 7 days at 50–70 °F. Sakrete's sheet says keep the surface moist for 3 to 5 days. Water curing must be continuous, not on-and-off.
Does concrete cure in cold weather?
Slowly. QUIKRETE notes that hydration slows considerably near freezing, which is why its curing period stretches from 5 to 7 days below 70 °F. Both QUIKRETE and Sakrete say to protect the concrete from freezing for the first 48 hours, using plastic sheeting and insulating blankets if temperatures will drop below 32 °F (0 °C).
How long does Quikrete take to set and dry?
It depends on the mix. QUIKRETE's Setting Posts sheet says Fast-Setting Concrete Mix sets in 20 to 40 minutes. Its regular Concrete Mix sheet gives no set or dry hour: keep it moist 5 days at 70 °F (21 °C) or warmer, 7 days at 50–70 °F, and wait 24 hours before putting any strain on a post.
How strong is concrete after 7 days?
For QUIKRETE Concrete Mix, about 2,500 psi (17.2 MPa) at 7 days against 4,000 psi (27.5 MPa) at 28 days, tested under ASTM C39. That is 62.5% of the 28-day figure. Ready-mix and other bagged products differ, so check the sheet or delivery ticket for your mix.
5 Sources
- QUIKRETE Setting Posts project sheet: Fast-Setting Concrete Mix sets in 20 to 40 minutes
- QUIKRETE Concrete Mix (No. 1101) data sheet, rev. Oct 2022: strength, curing periods, freeze protection, 24 h post wait
- Sakrete High-Strength Concrete Mix technical data sheet: 3–5 day moist cure, 48 h freeze protection
- ASTM C39/C39M: Compressive Strength of Cylindrical Concrete Specimens
- NIST SP 811 Appendix B.9: conversion factors
Last reviewed October 10, 2026 by M Bilal. Found an error? Tell us.