Key numbers
- Delivered price per yd³ = (yd³ × price + all fees) ÷ yd³
- Truckloads = ordered yd³ ÷ your plant's yd³ per truck, rounded up
- 1 yd³ of concrete weighs about 4,050 lb (1,837 kg)
- 80,000 lb: federal gross vehicle weight limit on Interstates (FHWA)
- Each $100 of flat fee adds $50 per yard on a 2 yd³ order, $12.50 on 8 yd³
On this page
- How to use the Concrete Delivery Cost
- How much does concrete delivery cost?
- What is a short-load fee and how much does it add per yard?
- How much is a yard of concrete delivered?
- How much concrete does a truck hold?
- How many truckloads do I need?
- What else drives the delivered price?
- How long can the truck wait before the concrete is too old?
- Is a small delivery or bagged concrete cheaper?
- Questions to ask before you book a delivery
- Common mistakes when pricing a concrete delivery
- Delivery cost vs price per yard: which page to use
- Frequently asked questions
How to use the Concrete Delivery Cost
- 1Choose the shapePick slab / pad, monolithic slab, round slab, footing, column / sonotube, post holes, steps, wall, curb & gutter, square / rect. column, beam or hollow cylinder. Each shape uses its own volume formula.
- 2Pick your unitsEvery dimension has its own unit menu (in, ft, yd, cm or m); changing one converts that number so the size stays the same. The US / Metric switch sets all fields to feet and inches or meters and centimeters and resets them to typical values.
- 3Enter the dimensionsType the length (default feet), width (default feet) or thickness (default inches). Measure the inside of the forms and the depth in several places.
- 4Set waste and quantityUse the waste slider (0 to 20%, default 10%) and allow more on uneven ground. If you have several identical pours, enter how many.
- 5Read the resultsSee the volume in cubic yards, cubic feet and cubic meters, the ready-mix order rounded up to ¼ yard, the number of 90, 80, 60, 50 and 40 lb bags rounded up, and the weight at the density you choose (150, 145 or 140 lb/ft³).
- 6Price it and save itPick a pricing basis (per cubic yard, per cubic meter or per bag of the highlighted size) and enter your local price for a material cost. Use Add to project to total several pours, and Copy link to share the exact result.
Results update as you type. Back to the calculator ↑

How much does concrete delivery cost?
Delivery cost is the concrete plus every fee the plant puts on the ticket. The concrete is your ordered yards times the quoted price per yard. The fees are flat charges, such as a short-load fee on small orders, a delivery or zone charge, waiting time and after-hours charges. We do not print a national average because each plant sets all of these; the calculator above takes your quote, and this page shows how to read it.
Delivered cost = ordered yd³ × price per yd³ + short-load fee + delivery, waiting and after-hours fees
- Get the volume. Enter your shape above; it adds waste (10% by default) and rounds up to the next ¼ yd³.
- Ask three questions. Price per yard for your mix, the short-load threshold and fee, and any delivery or zone charge.
- Enter the quote and add the flat fees to the total.
- Divide by the yards to get the delivered price per yard, the only number that compares plants fairly.
Worked example: 4 yd³ vs 5 yd³ with a short-load fee
- Example quote: $150 per yd³, plus a $200 short-load fee on orders under 5 yd³ (ask your plant for its real figures)
- 4 yd³: 4 × $150 + $200 = $800, or $200 per yard delivered
- 5 yd³: 5 × $150, no fee = $750, or $150 per yard
- Here the extra yard costs $50 less than the fee it avoids. Pour the spare into a pad, a step or post holes the same day.
What is a short-load fee and how much does it add per yard?
A short-load fee is a flat charge some plants add when your order is below their minimum load, because the truck makes the same trip mostly empty. Thresholds and amounts vary by plant, so treat both as inputs: ask “what is your minimum, and what is the fee below it?”
Because the fee is flat, its share falls as the order grows. The table shows what each $100 of fee adds to every yard; multiply by your fee ÷ 100.
| Order (yd³) | Order (m³) | Added per yd³ for each $100 of fee | Added per m³ for each $100 of fee |
|---|---|---|---|
| 1 | 0.76 | $100.00 | $130.80 |
| 1½ | 1.15 | $66.67 | $87.20 |
| 2 | 1.53 | $50.00 | $65.40 |
| 3 | 2.29 | $33.33 | $43.60 |
| 4 | 3.06 | $25.00 | $32.70 |
| 5 | 3.82 | $20.00 | $26.16 |
| 6 | 4.59 | $16.67 | $21.80 |
| 8 | 6.12 | $12.50 | $16.35 |
| 10 | 7.65 | $10.00 | $13.08 |
Per-m³ figures use 1 yd³ = 0.7646 m³ (NIST), so a per-yard figure × 1.308 is the per-m³ figure. The same table works for any other flat charge: a Saturday fee or a zone charge spreads over the yards in exactly the same way.
How much is a yard of concrete delivered?
The delivered price per yard is the whole ticket divided by the yards. It is always at least the quoted price, and on small orders it can be far higher. Using one set of example quotes ($150 per yard, $200 fee below 5 yd³) across order sizes shows the pattern:
| Order (yd³) | Order (m³) | Concrete at $150/yd³ | Short-load fee | Ticket total | Delivered per yd³ |
|---|---|---|---|---|---|
| 1½ | 1.15 | $225 | $200 | $425 | $283.33 |
| 2½ | 1.91 | $375 | $200 | $575 | $230.00 |
| 4 | 3.06 | $600 | $200 | $800 | $200.00 |
| 5 | 3.82 | $750 | none | $750 | $150.00 |
| 6 | 4.59 | $900 | none | $900 | $150.00 |
Totals come from the same cost function the calculator uses. The $150 and $200 are placeholders to show the arithmetic, not typical prices; swap in your plant’s figures. Notice the cliff at the threshold: just below it, ordering up can lower the total bill.
How much concrete does a truck hold?
Ask the plant’s dispatcher; the answer depends on the truck and the road rules where it drives, so we do not assume a figure. Two limits set it.
- Drum volume. A truck mixer is rated below the size of its drum so the load can tumble without spilling. Penn State’s ready-mix course notes say a drum used for truck mixing may hold 63% of its total volume, and up to 80% in central mixing.
- Weight. Concrete is heavy. At 150 lb/ft³ (the WSDOT design figure for normal-weight concrete), each cubic yard weighs about 4,050 lb. FHWA lists federal limits on the Interstate of 20,000 lb on a single axle, 34,000 lb on a tandem axle and 80,000 lb gross; off the Interstate, states set their own. So the legal load can be less than what the drum would hold.
| Load (yd³) | Load (m³) | Concrete weight (lb) | Concrete weight (kg) | US short tons |
|---|---|---|---|---|
| 1 | 0.76 | 4,050 | 1,837 | 2.03 |
| 4 | 3.06 | 16,200 | 7,348 | 8.10 |
| 8 | 6.12 | 32,400 | 14,696 | 16.20 |
| 9 | 6.88 | 36,450 | 16,533 | 18.23 |
| 10 | 7.65 | 40,500 | 18,370 | 20.25 |
The load sizes in this table are examples for the arithmetic, not a claim about any truck. Concrete weight excludes the truck, which is why 10 yd³ alone is already over half of 80,000 lb.
How many truckloads do I need?
Divide the ordered yards by the yards per truck your plant quotes, and round up. The last truck carries the remainder, which can be small.
Truckloads = ordered yd³ ÷ yd³ per truck, rounded up; last load = ordered yd³ − (truckloads − 1) × yd³ per truck
| Job | Calculated yd³ | Order +10% (yd³) | Order (m³) | Loads at 8 yd³ | Loads at 9 yd³ | Loads at 10 yd³ |
|---|---|---|---|---|---|---|
| 10 × 10 ft slab, 4 in | 1.23 | 1½ | 1.15 | 1 | 1 | 1 |
| 12 × 12 ft slab, 4 in | 1.78 | 2 | 1.53 | 1 | 1 | 1 |
| 100 ft footing, 16 × 8 in | 3.29 | 3¾ | 2.87 | 1 | 1 | 1 |
| 20 × 20 ft slab, 4 in | 4.94 | 5½ | 4.21 | 1 | 1 | 1 |
| 24 × 24 ft garage, 4 in | 7.11 | 8 | 6.12 | 1 | 1 | 1 |
| 24 × 24 ft garage, 6 in | 10.67 | 11¾ | 8.98 | 2 (last 3¾) | 2 (last 2¾) | 2 (last 1¾) |
| 12 × 60 ft driveway, 5 in | 11.11 | 12¼ | 9.37 | 2 (last 4¼) | 2 (last 3¼) | 2 (last 2¼) |
| 30 × 40 ft slab, 4 in | 14.81 | 16½ | 12.62 | 3 (last ½) | 2 (last 7½) | 2 (last 6½) |
| 40 × 60 ft slab, 4 in | 29.63 | 32¾ | 25.04 | 5 (last ¾) | 4 (last 5¾) | 4 (last 2¾) |
Volumes and loads come from scripts/concrete-delivery-cost.ts using the site’s calc library. Truck sizes of 8, 9 and 10 yd³ are illustrations; use your plant’s number.
Ask how a small last load is billed
On a multi-truck pour, a tiny last load (such as ½ yd³ on the 30 × 40 ft slab at 8 yd³ per truck) can be what the short-load rule was written for. Ask whether the fee applies per truck or per order, and whether the plant will balance the loads.
Worked example: 40 × 60 ft shop slab, 4 in thick
- 40 × 60 × 4 ÷ 324 = 29.63 yd³ (22.65 m³); +10% and rounded to ¼ yd³ = 32¾ yd³ (25.04 m³)
- At 10 yd³ per truck (ask your plant): 4 loads, three full and one with 2¾ yd³
- Concrete at an example $150 per yd³: 32¾ × $150 = $4,912.50, plus any per-truck or per-order fees
- Book the trucks spaced so each arrives as the crew finishes the last; a long gap leaves a cold joint
What else drives the delivered price?
Beyond the price per yard and the short-load fee, these lines move the ticket. Ask each plant about every one, and turn flat fees into a per-yard figure with the table above.
- Distance or zone. Some plants charge more beyond a set radius from the plant.
- Waiting time. A set unloading time is often included, then a charge applies. Have forms, base, tools and crew ready before the truck arrives.
- After-hours, weekend or holiday pours. Usually a flat fee.
- Mix and additives. Strength, fiber, color, accelerator in cold weather and retarder in hot weather are usually priced per yard.
- Placement. A pump or conveyor is quoted separately when the chute cannot reach the forms; estimate it with the concrete pump rental cost calculator.
- Washout. Ask where the driver can wash out the chute and whether that is your job to provide.
How long can the truck wait before the concrete is too old?
Ask the plant, and agree the limit when you order. ASTM C94/C94M-24d, the US ready-mixed concrete specification, no longer sets a fixed limit: the purchaser states a time limit to complete discharge (and any drum-revolution limit), and if none is stated the producer sets one, tells the purchaser before delivery and prints the time limit on the ticket. The standard notes that earlier editions, back to 1935, used 1½ hours. Some agencies still require 1½ hours and 300 drum revolutions on their projects, as California’s HCAI does for health-care buildings. For a home pour, the practical point is cost and quality: the longer the truck waits, the more waiting time you pay and the closer the load gets to its limit.
Is a small delivery or bagged concrete cheaper?
Compare the full ticket with the bags for the same volume. A 10 × 10 ft slab at 4 in, ordered as 1½ yd³, takes 68 × 80 lb bags (0.60 ft³ each, QUIKRETE data sheet). With the example quotes above, delivery is $425 ($283.33 per yard). The bag route costs 68 × your bag price, plus mixer rental and about 5,400 lb of dry mix to lift twice. Which wins depends on your bag price and your plant’s fee; the bags of concrete per yard table converts any order to bags.
Questions to ask before you book a delivery
One call to each plant gets every number this page needs:
- What is the price per yard, delivered, for the strength my job needs?
- What is your minimum load, and what is the fee below it? Is it per truck or per order?
- How many yards does each truck carry to my address?
- Is there a distance or zone charge?
- How much unloading time is included, and what does extra time cost?
- What is the time limit to finish discharge, and will it be on the ticket?
- Are Saturday, early or late pours extra?
- Can the truck reach my forms, and how much weight can my driveway or access take?
Common mistakes when pricing a concrete delivery
- Comparing quoted prices, not delivered prices. A lower price per yard with a short-load fee can cost more. Divide the ticket by the yards.
- Ordering just under the threshold. In the worked example, 4 yd³ with the fee ($800) cost more than 5 yd³ without it ($750).
- Running short. A second truck can mean a second fee and a cold joint. Add 10% and measure the base depth in several places.
- Guessing truck size. Plan loads from your plant’s figure, not an assumed one; weight limits differ by truck and by state.
- Forgetting access. A loaded truck weighs tens of thousands of pounds; keep it off septic tanks, thin slabs and soft ground.
Delivery cost vs price per yard: which page to use
Use this page to turn a plant’s quote into a delivered total and a truck count. Use concrete price per yard for what a yard buys in coverage and bags, and cost to pour a concrete slab to add labor, base and reinforcement. For volume first, start on the concrete calculator or the concrete yards calculator; for load weight, see the concrete weight calculator.
FAQ
Frequently asked questions
How much is 4 yards of concrete delivered?
4 × your plant's price per yard plus every fee on the ticket. With example quotes of $150 per yard and a $200 short-load fee below 5 yd³, that is $800, or $200 per yard. Ordering 5 yd³ at the same price avoids the fee and costs $750.
How much concrete does a truck hold?
Ask the plant: capacity depends on the drum size and on axle and gross weight limits. Weight adds up fast, because 1 yd³ is about 4,050 lb, so 10 yd³ is 40,500 lb of concrete before the truck itself. Federal Interstate limits are 80,000 lb gross (FHWA).
How much is a truck load of concrete?
Your plant's yards per truck × its price per yard, plus delivery fees. If a plant says its truck carries 10 yd³ and quotes an example $150 per yard, a full load is $1,500 of concrete. Full loads rarely carry a short-load fee, so they show the lowest delivered price per yard.
What is a short-load fee for concrete?
A flat charge some plants add when an order is below their minimum load. The threshold and amount vary by plant, so ask both. Spread over the yards, each $100 of fee adds $66.67 per yard on 1½ yd³ and $20 per yard on 5 yd³.
What is the minimum order for ready-mix concrete?
Each plant sets its own, and some deliver any amount but charge a short-load fee below a threshold. Ask for the threshold in cubic yards. A 10 × 10 ft slab at 4 in needs 1.23 yd³, so a 1½ yd³ order with 10% extra is a small load at most plants.
How much is a yard of concrete delivered?
Add the ticket total and divide by the yards. With an example $150 per yard and a $200 fee below 5 yd³, 2½ yd³ works out to $230 per yard delivered and 6 yd³ to $150. Use your own plant's price and fee in the same sum.
How long can a concrete truck wait on site?
Ask the plant: it sets the free unloading time and the waiting charge. Under ASTM C94/C94M-24d the purchaser, or else the producer, sets the time limit to finish discharge, and it is printed on the ticket. Older editions used 1½ hours.
How many concrete trucks do I need for a 40x60 slab?
A 40 × 60 ft slab at 4 in is 29.63 yd³, or 32¾ yd³ ordered with 10% extra. At 10 yd³ per truck that is 4 loads, the last carrying 2¾ yd³; at 8 yd³ it is 5 loads. Use your plant's truck capacity.
6 Sources
- ASTM C94/C94M-24d sections 6.1.9, 6.1.10 and Note 10 (purchaser/producer set discharge time and drum-revolution limits; previous 1½ h limit), as quoted in California HCAI Policy Intent Notice 82, effective 9 Oct 2025
- FHWA Office of Freight Management: federal size and weight limits (20,000 lb single axle, 34,000 lb tandem, 80,000 lb gross on the Interstate)
- Penn State CE 584 course library, Truck Mixers: a drum may hold 63% of its total volume for truck mixing and up to 80% in central mixing
- Washington State DOT Bridge Design Memo 05-2010: unit weight of normal-weight concrete 150 lb/ft³
- NIST SP 811 Appendix B.9: 1 yd³ = 0.7645549 m³
- QUIKRETE Concrete Mix (No. 1101) data sheet: 80 lb bag yield 0.60 ft³
Last reviewed October 10, 2026 by M Bilal. Found an error? Tell us.